M. M. ENGG. COLLEGE TEAM MOLTRES ESVC030
Design Validation Plan Team name: Night Fury Team ID :Esvc030 Vehicle owner: Team Night Fury,
College name: Maharishi Markandeshwar Engg. College, Ambala (Hry.) Testing time period: 10 days DVP creator: Shazi Munir
M.M. ENGG. College Vehicle design: Praveen Bagoti
Technical assistant: Sandeep Saini
Test of
Test name
Test method
Acceptance criteria
Location Remark of test
Assigned to
Brakes
Bleeding test
Continuously pressing the peddle & check for any leakage.
If no leakage then braking is under safe condition.
Workshop
Add more fluid & tighten the hose and connector
Mayank
Panic brake test
At 40 kmph brakes If all wheels are locked are applied & check properly, braking is for locking of all efficient wheel.
University ground
If all the wheels do not lock on operation of brakes then bleeding has to be done
Hasan Anjum
Stopping distance test
Run vehicle at max speed, apply brake & check stopping distance
University ground
If efficiency is less than 80% then increase leverage ratio & check for peddle force
Abhishek
Braking Efficiency accepted at 80 % under working.
Page 1
Roll cage
Steering
M. M. ENGG. COLLEGE TEAM MOLTRES ESVC030
Material selection
Using material having the carbon content of min 0.18% conduct various test tension ,shear, buckling etc
The result should satisfy the parameters to be obtained in main event
Material testing lab
In any problem consider high carbon content
Mukesh Gupta
Weld strength
After completion of fabrication throw the roll cage from top &check for any bend & crack in welded area
There should not be any bend or crack at welded area
A high podium
If failure occur welding is done again, until the required strength is obtained
Tapan
Maneuver-ability test
Drive the vehicle on 2m zigzag path without stopping & travelling at much corner without crossing the boundary
The vehicle should move within the path easily & steering should be smooth & easy
Bumpy track
Adjust the component in any failure
Parth
Drive vehicle on a smooth track and note readings of Tachometer and Speedometer and compare the readings with ideal
Results should be as close as possible to ideal curve
Smooth Track
In case of large deviation from ideal curve make adjustments with motor and motor controller for proper tuning.
Pankaj and Nadir
Transm Tuning Test -ission
Page 2
Engine
M. M. ENGG. COLLEGE TEAM MOLTRES ESVC030
Efficiency test
calculating voltage and current by multimeter , calculating power by using wattmeter to draw various graphs
Efficiency should match near about the given efficiency of the
Load test at no load
To check maximum rpm and minimum current To check maximum torque and maximum current
Rated rpm should be obtained at no load
Load test at full load
Rated current should be obtained for maximum torque for movement of vehicle
Page 3
workshop
Proper inclination of and proper insulation to prevent short circuiting
Indrajit & Akshay Dogra