METHOD STATEMENT Title : Method Statement For Installation Of Electric PVC Conduits And Accessories
Page : 2 of 9
Reference :
TABLE OF CONTENT
ITEM NO.
-
TITLE
PAGE
TABLE OF CONTENT
1.0
OBJECTIVE
3
2.0
SCOPE
3
3.0
HANDLING AND STORAGE
3
4.0
WORK METHODOLOGY
3-4
5.0
RESPONSIBILITY
6
6.0
EQUIPMENT
7
7.0
TYPICAL INSTALLATION ARRANGEMENT LAYOUT
8
8.0
SAFETY, HEALTH, SECURITY AND ENVIRONMENT
9
METHOD STATEMENT Title : Method Statement For Installation Of Electric PVC Conduits And Accessories
Page : 3 of 9
Reference :
1.0
OBJECTIVE This method statement explains the detailed requirements and procedures for the installation of PVC Conduits and accessories in the concrete slabs, columns, block works and concrete walls.
2.0
SCOPE This procedure applies to project site which requires installation of electric PVC conduits and its accessories inside and outside the building.
2.0
3.0
HANDLING AND STORAGE 2.1
Deliver components parts and material to site, completely identified in accordance with approved brand and supplier and also comply with certified drawings prepared for this work.
2.2
Store in accordance with the manufacturer’s instructions, above ground, properly protected from the weather and construction activities.
WORK METHODOLOGY
3.1
Material: Material used will be as approved by the engineer. The sizes and routes routing will be as per the approved shop drawing.
3.2
Installation 1.
During the course of the installation of the conduit system, procedures for working and dressing the installation as recommended shall be employed.
2.
All bends and sets shall be in accordance with IEE regulation 522-08 formed with the aid of a helical spring fitted internally, with if necessary,
METHOD STATEMENT Title : Method Statement For Installation Of Electric PVC Conduits And Accessories
Page : 4 of 9
Reference :
3.3
3.
Conduit system shall be installed so as to ensure compliance with the requirements of Specified Standard and Regulation.
4.
ts between PVC conduit + fittings shall be made with suitable adhesive, but expansion couplings shall be installed where any length of conduit, inclusive of draw in boxes etc, exceeds five meters in length.
5.
The minimum and maximum sizes of conduit to be employed shall be ¾ inch and 1 inch respectively, unless otherwise stated in subsequent sections of the specification.
6.
Conduits in floors shall be routed and installed so as to avoid the fixings of floor standing equipment to be installed on the floor.
Fixing of Conduits
1. When conduits are run on shuttering, prior to the laying of concrete in-situ, additional security must be provided near to every box and at intervals of not more than 1.2 meters by binding short lengths of steel wire, of not less than 2mm diameter twisted around the conduit and reinforcing steel. The conduits shall be adequately fixed to prevent excessive movement and damage during the pouring and setting of concrete and shall be protected from mechanical damage. Check there is no damage before screed / concrete is poured. Unless otherwise indicated to cast in conduits shall not be less than 30mm.cores to plastered over conduits shall not be less than 5mm. 2. Where conduits are left "open ended" prior to wiring they shall be protected by caps or plugs to prevent the ingress of building material. 3. All conduits runs must be designed to permit wiring to be readily installed after the complete erection of the conduits through the available draw-in, accessory and luminary suspension boxes. 4. Where surface mounted equipment (other than luminaries) is specified, all concealed conduits shall be terminated and an adaptable box installed recessed into the wall at every surface mounted equipment position.
METHOD STATEMENT Title : Method Statement For Installation Of Electric PVC Conduits And Accessories
Page : 5 of 9
Reference :
5. Where conduits through an external wall/roof the conduit box shall be fitted on the side and after wiring filled with an inert, permanently plastic compound having a high insulation value. 6. Make provision in conduit and trunking, installation where building expansion ts are crossed or settlement is likely. 7. Ensure conduits are not concealed until works has been inspected and approved. Ensure that conduit and fittings buried in concrete or behind plaster are protected against corrosion or electrolytic action prior to rendering.
4.0
RESPONSIBILITY
Project Manager: o o o o
Site Engineer: o o o o
To ensure that all the preparation and application works are carried out according to the Contract Specification and with the approved drawings. To ensure that the progressing of work is carried out according to the planned program and as per the approved method of statement. To ensure that all the equipment and materials required executing the work are available according to the planned construction program. To co –ordinate with the Main contractor, MEP Coordinator and Safety Officer, for a safe and proper execution of the works.
To ensure that the works are carried out according to the Contract Specifications, approved method statement and the shop drawings. To provide all necessary information and distribute responsibilities to his construction team. To monitor the progress of work in relation with the work program and to report to the Project Manager. To co-ordinate with the safety officer and to ensure that the works are carried out in safe practicing methods.
Foreman: o
The foreman will carry out his duties by maintaining continuous coordination with the site engineer on daily basis, and ensure proper distribution of the workforce in the required and planned locations.
METHOD STATEMENT Title : Method Statement For Installation Of Electric PVC Conduits And Accessories
Page : 6 of 9
Reference :
o
To ensure that his assistant foreman/ charge hand are aware of the job requirements and they have enough information to carry out their duties properly. To ensure in consultation with the site engineer that the manpower involved in the works are moving as agreed and planned for the work. To ensure that the daily work is progressing as planned and advice the site engineer of any requirement for additional resources. To control disposal of waste materials according to the instructions received from the site engineer. To ensure full coordination with the safety officer to maintain safe working and proper housekeeping of the site, following the approved safety measures and further ensure that all his working team are aware of the same to prevent accident and losses. To inform the site engineer and of the areas ready for inspection. Distribution and the control of material shall be monitored by foreman and store keeper.
o o o o
o o
5.0
EQUIPMENT The requirements that will be engaged for PVC conduiting works will be as follows: 1. 2. 3. 4. 5. 6.
Hack saw Measuring tape Cutting plier Knipex (End cutter) Bending spring Drilling Machine
METHOD STATEMENT Title : Method Statement For Installation Of Electric PVC Conduits And Accessories
Page : 7 of 9
Reference :
6.0
TYPICAL INSTALLATION ARRANGEMENT LAYOUT
Method Statement for Installation Of Electrical PVC Conduits And Accessories In The Concrete Slabs, Columns, Block Works And Concrete Walls
METHOD STATEMENT Title : Method Statement For Installation Of Electric PVC Conduits And Accessories
Page : 8 of 9
Reference :
7.0
ITP Clause No.
1
2
QUALITY ASSURANCE PLAN
Inspection Description
Design and Drawings
Material Approval
Type of Inspection
Reference Document
Testing Requirement/ Acceptance Criteria
ing / Control Data Forms
Review of Documents
Design Drawings
All the Drawings
Design Drawings, Authorities Departments Requirements
Review of Documents
Approved Drawing, Specification
Should be as per the approved drawing and Specification
Documents Submittals
Approved Method Statement
Proper bends correct height and Location, material should have minimum status on – No Objection with comments (2)
Approved Drawing Method Statement
Approved Drawings
NO obstructions height, Proper position
Approved Drawings
3
Check installation of PVC Conduits
Visual
4
Raise inspection request
Visual Measurement instrument
METHOD STATEMENT Title : Method Statement For Installation Of Electric PVC Conduits And Accessories
Page : 9 of 9
Reference :
8.0
SAFETY, HEALTH, SECURITY AND ENVIRONMENT
Strictly follow as per the manufacturer’s Health and Safety recommendations for handling and used of the materials. Ensure all involved personnel shall be aware of the same. A special safety inspector is assigned; all personnel involved in this work shall use the mandatory P.P.E as follows. Safety Helmet b. Safety Shoes/Boots c. Safety glasses. d. All other PPE as required by the risk assessment. a.
All work will be undertaken by qualified competent persons with experience of the type of work described above, and in all cases in full accordance with safety procedures specified in the company's health and safety Policy.