PRESUPUESTO GENERAL Uunidad Educativa “San Daniel Comboni”
Edificio C-2
COSTO 255,344.41 255,344.41 255,344.41
z EDIFICIO C-2
1
Unidad u
A Taller de Industria del Alimento z TALLER DE INDUSTRIA DEL ALIMENTO
1
u
589,754.75
589,754.75 589,754.75
B Aulas Educacion Inicial z AULA TIPO EDUCACION INICIAL
3
u
32,153.69
96,461.07 96,461.07
C Obras Exteriores z OBRAS EXTERIORES
1
u
11,243.48
11,243.48 11,243.48
D Pozo Absorvente z POZO ABSORVENTE
1
u
1,009.07
1,009.07 1,009.07
G Baterias Sanitarias z BATERIA SANITARIA 150 P
1
u
12,696.42
12,696.42 12,696.42
TOTAL:
QUITO, 19 DE ABRIL DEL 2010
No.
966,509.20
ABICEC CONSTRUCTORA CIA. LTDA OFERENTE
1 51,068.88
2 51,068.88
3 51,068.88
CRONOGRAMA VALORADO (MESES) 4 5 51,068.88
58,975.48
58,975.48
58,975.48
58,975.48
24,115.27
24,115.27
24,115.27
24,115.27
134,159.62 14% 134,159.62 14%
134,159.62 14% 268,319.25 28%
134,159.62 14% 402,478.87 42%
134,159.62 14% 536,638.50 56%
6
7
51,068.88
58,975.48
58,975.48
58,975.48
110,044.36 11% 646,682.86 67%
58,975.48 6% 705,658.33 73%
58,975.48 6% 764,633.81 79%
8
58,975.48
9
10
58,975.48
58,975.48
5,621.74
5,621.74
1,009.07
12,696.42
58,975.48 6% 823,609.28 85%
64,597.22 7% 888,206.50 92%
78,302.71 8% 966,509.20 100%
CONTRATO: MURO DE MAMPOSTERIA DE LADRILLO
PLAZO DE EJECUCION:
30 DIAS
OFERENTE: POLIVIO CALLE
FECHA:
MAYO DEL 2010
MONTO DE LA OFERTA:
$5,328.46
HOJA 1 DE 1
UBICACION: CUENCA, SECTOR TOTORACOCHA CRONOGRAMA RUBRO 1
DESCRPCION REPLANTEO Y NIVELACION
UNIDAD m
VALORADOS DE TRABAJOS
CANTIDAD
PRECIO
PRECIO
30.00
UNITARIO 0.83
TOTAL $24.90
2
EXCAVACION DE CIMIENTOS
m3
6.00
9.33
$55.98
3
CARGADO DE MATERIAL A MANO
m3
7.8
3.23
$25.19
4
DESALOJO DE MATERIAL
m3
7.80
3.06
$23.87
4
HORMIGON CICLOPEO f'c=180 kg/cm2
m3
6.00
93.55
$561.30
5
ENCOFRADO RECTO
m2
18.40
8.80
$161.92
6
ACERO DE REFUERZO f`y=4200 kg/cm2
kg
225.72
1.73
$390.50
7
HORMIGON SIMPLE PARA CADENAS Y COLUMNAS
m3
1.52
140.74
$213.92
8
MAMPOSTERIA DE LADRILLO
m2
118.40
18.20
$2,154.88
ENLUCIDO VERTICAL INT/EXT.
m2
240.00
7.15
$1,716.00
TIEMPO EN DIAS 7 dias 100.00% 24.90 100.00% 55.98 100.00% 25.19 100.00% 23.87 20.00% 112.26
7 dias
7 dias
7 dias 100
40.00% 224.52 50.00% 80.96
50.00% 106.96 50.00% 1,077.44
95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15
40.00% 224.52 50.00% 80.96 100.00% 390.50 50.00% 106.96 50.00% 1,077.44 50.00%
50.00%
10
858.00
858.00
5 0
$5,328.46 INVERSION PARCIAL
242.20
1,489.88
2,738.38
4.55
27.96
51.39
16.10
242.20
1,732.08
4,470.46
5,328.46
AVANCE ACUMULADO EN %
4.55
32.51
83.90
100.00
CURVA DEL 80 %
3.64
26.91
69.07
100
AVANCE PARCIAL EN % INVERSION ACUMULADA
80% 100%
858.00
$0.00 NOMBRE: POLIVIO CALLE - XAVIER GUNCAY OBRA: PROGRAMACION DE OBRAS
FORMULARIO No. 11
UBICACIÓN: UAED - UCACUE
HOJA 1 DE 1 CRONOGRAMA
RUBRO
DESCRPCION
UNIDAD
CANTIDAD
PRECIO
1
PRELIMINARES
u
1.00
UNITARIO 2913.27
2
MOVIMIENTOS DE TIERRAS
u
1.00
101740.97
3
ESTRUCTURA DE CIMENTACION
u
1.00
70176.81
4
ESTRUCTURA
u
1.00
286205.04
5
MAMPOSTERIA
u
1.00
31055.79
6
ENLUCIDOS
u
1.00
109630.92
7
RECUBRIMIENTOS
u
1.00
40090.71
8
PISOS
u
1.00
49418.91
9
CARPINTERIA METAL / MADERA
u
1.00
64211.89
10
INSTALACIONES SANITARIAS
u
1.00
23426.38
11
SISTEMA DE VENTILACION
u
1.00
4144.54
12
INSTALACIONES ELECTRICAS
u
1.00
81777.20
13
ESTRUCTURA Y CUBIERTA METALICA
u
1.00
36668.92
14
RED DE ALCANTARILLADO DE AGUAS SERVIDAS
u
1.00
3194.88
15
POZOS DE INSPECCION
u
1.00
1775.19
16
OBRAS EXTERIORES
u
1.00
41192.42
17
OBRAS ESPECIALES
u
1.00
86.45
18
VARIOS
u
1.00
5093.42
19
POZO ABSORVENTE
u
1.00
1009.07
20
BATERIA SANITARIA 150 P
u
1.00
12696.42
INVERSION MENSUAL AVANCE PARCIAL EN % INVERSION ACUMULADA AVANCE ACUMULADO EN %
VALORADOS DE TRABAJOS TIEMPO EN DIAS
30 dias 1.00 2,913.27 0.30 30,522.29 0.40 28,070.72
30 dias
0.40 30,522.29 0.60 42,106.09 0.20 57,241.01
30 dias
30 dias
30 dias
30 dias
30 dias
30 dias
30 dias
0.30 40,696.39
0.20 57,241.01 0.20 6,211.16 0.10 10,963.09
0.20 57,241.01 0.20 6,211.16 0.10 10,963.09
0.20 57,241.01 0.20 6,211.16 0.20 21,926.18
0.10 28,620.50 0.20 6,211.16 0.20 21,926.18
0.10 28,620.50 0.20 6,211.16 0.20 21,926.18
0.20 21,926.18 0.50 20,045.36 0.50 24,709.46 0.50 32,105.95
0.20 4,685.28
30 dias
0.20 4,685.28
0.20 4,685.28
0.20 4,685.28
0.50 20,045.36 0.50 24,709.46 0.50 32,105.95
0.20 4,685.28 1.00 4,144.54
0.20 16,355.44
0.20 16,355.44
0.60 49,066.32 1.00 36,668.92
1.00 3,194.88 1.00 1,775.19 1.00 41,192.42 1.00 86.45 1.00 5,093.42 1.00 1,009.07 0.50 6,348.21
0.50 6,348.21
61,506.29
154,104.98
136,152.36
115,769.45
90,063.63
61,443.12
110,487.42
79,115.90
76,860.76
6.36
15.94
14.09
11.98
9.32
6.36
11.43
8.19
7.95
81,005.30 8.38
61,506.29
215,611.27
351,763.63
467,533.08
557,596.71
619,039.83
729,527.25
808,643.15
885,503.91
966,509.20
6.36
22.31
36.40
48.37
57.69
64.05
75.48
83.67
91.62
100.00
FORMULARIO No. 2 NOMBRE: POLIVIO CALLE - XAVIER GUNCAY
HOJA 1
DE 4
OBRA: PROGRAMACION DE OBRAS UBICACIÓN: UAED - UCACUE
CUADRO DE CANTIDADES Y PRECIOS RUBRO
DESCRIPCION
UNIDAD
CANTIDAD
P. UNITARIO
P. TOTAL
EDIFICIO C-2 1
PRELIMINARES
2
REPLANTEO Y NIVELACION
m2
378.98
MOVIMIENTOS DE TIERRAS
0.83 SUB-TOTAL =
314.55 314.55
1
EXCAVACION DE CIMIENTOS CON MAQUINARIA
m3
210.15
2.33
2
RELLENO Y COMPACTACION CON SUELO NATURAL
m3
97.42
3.71
361.43
3
CAMBIO DE SUELO CON LASTRE COMPACTADO EN PLINTOS Y ACERAS
m3
40.29
32.20
1,297.34
4
DESALOJO DE MATERIAL
m3
112.73
3.39
ESTRUCTURA DE CIMENTACION
489.65
382.15 2,530.57
1
REPLANTILLOS H.S. f'c=140 kg/cm2
m2
103.38
7.39
2
REPLANTILLO DE PIEDRA BOLA e=10 cm
m2
103.38
5.47
565.49
3
HORMIGON SIMPLE EN ZAPATAS CORRIDAS f'c=210 kg/cm2
m3
10.52
171.50
1,804.18
4
HORMIGON SIMPLE EN PLINTOS f'c=210 kg/cm2
m3
39.80
145.84
5,804.43
5
MURO DE HORMIGON CICLOPEO f'c=180 kg/cm2
m3
17.92
93.55
1,676.42
6
HORMIGON SIMPLE EN CADENAS INFERIORES f'c=210 kg/cm2
m3
13.44
178.95
2,405.09
7
ACERO DE REFUERZO f`y=4200 kg/cm2
kg
2,848.03
1.75
ESTRUCTURA PLANTA BAJA
763.98
4,984.05 18,003.64
1
REPLANTILLO DE PIEDRA BOLA e=10 cm
191.44
5.47
2
RELLENO CON LASTRE (AMARILLO), COMPACTADO PARA CONFORMACION DE CONTRAPISO m3 H=0,23 m44.03
m2
12.80
563.58
3
HORMIGON SIMPLE EN CONTRAPISO H.S. e=10 cm f'c=180 kg/cm2 INC. MALLA ELECTROSOLDADA m2
210.10
19.69
4,136.87
4
HORMIGON SIMPLE f'c=210 kg/cm2 EN COLUMNAS
m3
15.89
218.04
3,464.66
5
HORMIGON SIMPLE EN LOSAS DE ENTREPISO f'c=210 kg/cm2
m3
27.82
203.82
5,670.27
6
HORMIGON SIMPLE EN VISERA POSTERIOR f'c=210 kg/cm2
m3
2.88
203.82
587.00
7
BLOQUE DE POMEZ DE 0.15x0.20x0.40 m (EN LOSA)
u
2,248.00
0.47
1,056.56
8
RIOSTRAS H. ARMADO 15x10, EN PUERTAS Y VENTANAS
ml
170.30
12.09
2,058.93
9
HORMIGON SIMPLE EN VIGAS SUPERIORES f'c=210 kg/cm2
m3
24.28
220.73
5,359.32
10
MALLA ELECTROSOLDADA 15x15 ø 6 mm
m2
54.50
7.21
392.95
11
ACERO DE REFUERZO f`y=4200 kg/cm2
kg
9,389.95
1.75
16,432.41
m2
279.71
11.56
MAMPOSTERIA
1,047.18
40,769.73
1
MAMPOSTERIA BLOQUE e= 15 cm
2
MESON PARA LAVAMANOS CON CERAMICA DE 3.35x0.60 m
u
1.00
94.08
94.08
3
MESON PARA LAVAMANOS CON CERAMICA DE 3.80x0.60 m
u
1.00
109.54
109.54
ENLUCIDOS
3,233.45
3,437.07
1
ENLUCIDO VERTICAL INT/EXT.
m2
722.10
9.24
6,672.20
2
ENLUCIDO DE CIELO RASO
m2
310.05
8.13
2,520.71
3
ENLUCIDO DE VISERA POSTERIOR
m2
59.37
9.24
548.58
4
ENLUCIDO FILOS DE PUERTAS Y VENTANAS
ml
170.30
2.29
389.99
5
ENLUCIDO FILOS DE VIGAS
m
137.00
3.91
535.67
6
ENLUCIDO FILOS DE COLUMNAS
m
184.32
3.91
720.69
7
FORRADO DE BAJANTES AA. LL. CON MALLA NERVADA Y MORTERO 1:3
ml
35.00
4.90
171.50
8
GOTERO EN FACHADA PRINCIPAL
ml
40.00
3.87
154.80
9
GRAFEADO EN PAREDES DE OFICINAS
m2
108.17
6.08
657.67
10
CHAFADO DE CIELO RASO EN OFICINAS
m2
50.20
6.67
RECUBRIMIENTOS
334.83 12,706.64
1
PINTURA DE CAUCHO INTERIOR
m2
575.71
3.54
2,038.01
2
PINTURA DE CAUCHO EXTERIOR
m2
323.19
3.77
1,218.43
3
PINTURA DE CAUCHO EN VISERA POSTERIOR
m2
59.37
3.77
223.82
4
CERAMICA PARA PARED EN BAÑOS H=2,00 m
m2
161.80
18.90
3,058.02
PISOS PLANTA BAJA
6,538.28
1
BALDOSA GRANITICA PARA PISOS (30x30) PULIDA
m2
154.00
21.62
3,329.48
2
BALDOSA CERAMICA PARA PISOS
m2
56.11
15.98
896.64
3
BARREDERA INTERIOR DE BALDOSA GRANITICA H=15 cm
ml
59.70
3.33
198.80
4
BARREDERA INTERIO DE BALDOSA CERAMICA H=15 cm
m
38.30
2.86
CARPINTERIA METAL / MADERA
109.54 4,534.46
1
CERRADURA LLAVE SEGURO-PUERTA EXTERIOR
u
18.00
15.02
270.36
2
PUERTA LAQUEADA DE DORMITORIO 1.00x2.10 SIN TARJETA
u
5.00
224.74
1,123.70
3
PUERTA LAQUEADA DE LAUREL 0.70x2.10 m INC. CHAPA DE POMO
u
2.00
193.47
386.94
4
PUERTA LAQUEADA DE LAUREL 0.70x1.80 INC. PICAPORTE DE BRONCE
u
10.00
156.30
1,563.00
5
VENTANA DE ALUMINIO CON VIDRIO TRANSPARENTE e= 4 mm
m2
11.70
66.73
780.74
6
CONTRAVENTANAS DE HIERRO SEGÚN DISEÑO
m2
50.70
30.94
1,568.66
7
MANIGUETA DE BRONCE DE 4” EN PUERTAS
u
6.00
3.10
INSTALACIONES SANITARIAS
18.60 5,712.00
1
SALIDA DE AGUA POTABLE 1/2"
pto
27.00
17.64
476.28
2
DESAGUE PVC 110 mm
pto
10.00
24.21
242.10
3
DESAGUE PVC 50 mm
pto
21.00
15.07
316.47
4
INODORO TANQUE BAJO COLOR BLANCO
u
10.00
95.22
952.20
5
LAVAMANOS CON PEDESTAL BLANCO
u
2.00
100.93
201.86
6
LAVAMANOS
u
9.00
59.45
535.05
7
URINARIO DE COLOR BLANCO
u
4.00
152.33
609.32
8
DUCHAS
u
2.00
14.25
28.50
9
ACOMETIDA DE AGUA POTABLE
ml
20.00
2.98
59.60
10
LLAVE DE PASO Y CONTROL
u
6.00
9.89
59.34
11
BAJANTES DE AGUAS LLUVIAS
ml
76.46
5.24
400.65
12
BAJANTES Y conexión DE AGUAS SERVIDAS
ml
112.70
6.15
693.11
13
CAJAS DE REVISION EXTERIOR DE 0,60x0,60x0.80 CON TAPA
u
8.00
76.92
615.36
14
CAJAS DE REVISION EXTERIOR DE 0,80x0,80x1,30 CON TAPA
u
2.00
103.30
ESTRUCTURA DE BLOQUE DE GRADAS EN PLANTA BAJA
206.60 5,396.44
1
REPLANTILLO DE PIEDRA BOLA e=10 cm
14.43
5.47
2
RELLENO CON LASTRE (AMARILLO), COMPACTADO PARA CONFORMACION DE CONTRAPISO m3 H=0,23 m 1.44
m2
12.80
18.43
3
HORMIGON SIMPLE EN CONTRAPISO H.S. e=10 cm f'c=180 kg/cm2 INC. MALLA ELECTROSOLDADA m2
17.97
19.69
353.83
4
HORMIGON SIMPLE f'c=210 kg/cm2 EN COLUMNAS
2.54
218.04
553.82
5
RIOSTRAS H. ARMADO ARMADURA ELECTROSOLDADA, SECCION 10x10, 4ø 7 mm, 1 mle ø 4 mm @ 0.15 m 4.00
9.54
38.16
6
HORMIGON SIMPLE EN GRADAS f'c=210 kg/cm2
m3
3.87
182.16
704.96
7
HORMIGON SIMPLE EN LOSETA DE GRADAS f'c=210 kg/cm2
m3
0.64
182.16
116.58
8
BLOQUE DE POMEZ DE 0.15x0.20x0.40 m (EN LOSA)
u
45.00
0.47
21.15
9
HORMIGON SIMPLE EN VIGAS SUPERIORES f'c=210 kg/cm2
m3
2.52
220.73
556.24
10
ACERO DE REFUERZO f`y=4200 kg/cm2
kg
686.96
1.75
1,202.18
m2
35.39
11.56
m3
MAMPOSTERIA 1
MAMPOSTERIA BLOQUE e= 15 cm
78.93
3,644.28
ENLUCIDOS
409.11 409.11
1
ENLUCIDO VERTICAL INT/EXT.
m2
72.61
9.24
670.92
2
ENLUCIDO DE CIELO RASO
m2
14.73
8.13
119.75
3
ENLUCIDO FILOS DE VIGAS
m
36.58
3.91
143.03
4
ENLUCIDO FILOS DE COLUMNAS
m
25.47
3.91
RECUBRIMIENTOS 1
PINTURA DE CAUCHO EXTERIOR
m2
100.92
3.77
m2
23.41
21.62
m2
5.60
38.62
216.27 158.50
PISOS EN BLOQUES DE GRADAS 1
BALDOSA GRANITICA PARA PISOS (30x30) PULIDA
506.12 506.12
1
REJAS EN ESCALERA
2
PUERTA METALICAS EN BAÑOS
u
2.00
79.25
3
PUERTA METALICAS EN ESCALERAS (3.80x2.80)
u
1.00
702.72
INSTALACIONES SANITARIAS BAJANTES DE AGUAS LLUVIAS
380.47 380.47
CARPINTERIA METAL / MADERA
1
99.59 1,033.29
702.72 1,077.49
ml
3.24
5.24
SEGUNDO PISO
16.98 16.98
ESTRUCTURAS 1
HORMIGON SIMPLE f'c=210 kg/cm2 EN COLUMNAS
m3
11.34
218.04
2,472.57
2
HORMIGON SIMPLE EN LOSAS DE ENTREPISO f'c=210 kg/cm2
m3
27.82
203.82
5,670.27
3
HORMIGON SIMPLE EN VISERA POSTERIOR f'c=210 kg/cm2
m3
2.88
203.82
587.00
4
BLOQUE DE POMEZ DE 0.15x0.20x0.40 m (EN LOSA)
u
2,248.00
0.47
1,056.56
5
RIOSTRAS H. ARMADO 15x10, BALCON
ml
40.33
15.68
632.37
6
RIOSTRAS H. ARMADO 15x10, EN PUERTAS Y VENTANAS
ml
161.20
12.09
1,948.91
7
HORMIGON SIMPLE EN VIGAS SUPERIORES f'c=210 kg/cm2
m3
24.28
220.73
5,359.32
8
MALLA ELECTROSOLDADA 15x15 ø 6 mm
m2
54.50
7.21
392.95
9
ACERO DE REFUERZO f`y=4200 kg/cm2
kg
9,389.95
1.75
16,432.41
m2
198.94
11.56
MAMPOSTERIA 1
MAMPOSTERIA BLOQUE e= 15 cm
34,552.36 2,299.75
2
MAMPOSTERIA BLOQUE e= 15 cm, EN BALCON
m2
20.62
11.58
ENLUCIDOS
238.78 2,538.53
1
ENLUCIDO VERTICAL INT/EXT.
m2
499.64
9.24
4,616.67
2
ENLUCIDO DE CIELO RASO
m2
310.05
8.13
2,520.71
3
ENLUCIDO DE VISERA POSTERIOR
m2
59.37
9.24
548.58
4
ENLUCIDO VERTICAL DE BALCON
m2
41.24
9.24
381.06
5
ENLUCIDO FILOS DE PUERTAS Y VENTANAS
ml
161.20
2.29
369.15
6
ENLUCIDO FILOS DE VIGAS
m
137.00
3.91
535.67
7
ENLUCIDO FILOS DE COLUMNAS
m
233.28
3.91
912.12
8
FORRADO DE BAJANTES AA. LL. CON MALLA NERVADA Y MORTERO 1:3
ml
73.00
4.90
357.70
9
GOTERO EN FACHADA PRINCIPAL
ml
40.00
3.87
RECUBRIMIENTOS
154.80 10,396.46
1
PINTURA DE CAUCHO INTERIOR
m2
628.34
3.54
2,224.32
2
PINTURA DE CAUCHO EXTERIOR
m2
222.59
3.77
839.16
3
PINTURA DE CAUCHO EN VISERA POSTERIOR
m2
59.37
3.77
PISOS
223.82 3,287.30
1
BALDOSA GRANITICA PARA PISOS (30x30) PULIDA
m2
269.08
21.62
2
BARREDERA INTERIOR DE BALDOSA GRANITICA H=15 cm
ml
119.40
3.33
SISTEMA DE VENTILACION
5,817.51 397.60 6,215.11
1
AIRE ACONDICIONADO DE 36000 BTU CENTRO DE COMPUTO
global
1.00
2,278.77
2,278.77
2
AIRE ACONDICIONADO DE 24000 BTU CENTRO DE IDIOMAS
global
1.00
1,865.77
1,865.77
CARPINTERIA METAL / MADERA
4,144.54
1
CERRADURA LLAVE SEGURO-PUERTA EXTERIOR
u
4.00
15.02
60.08
2
PUERTA LAQUEADA DE DORMITORIO 1.00x2.10 SIN TARJETA
u
4.00
224.74
898.96
3
CONTRAVENTANAS DE HIERRO SEGÚN DISEÑO
m2
63.96
30.94
1,978.92
4
VENTANA DE ALUMINIO CON VIDRIO TRANSPARENTE e= 4 mm
m2
31.98
66.73
2,134.03
5
PASAMANOS DE MADERA DORMILON
ml
31.81
33.46
1,064.36
6
MANIGUETA DE BRONCE DE 4” EN PUERTAS
u
4.00
3.10
INSTALACIONES SANITARIAS
12.40 6,148.75
1
BAJANTES DE AGUAS LLUVIAS
ml
25.92
5.24
135.82
2
DESAGUES Y REJILLA DE PISO PVC /D; ø =75 mm
pto
8.00
22.20
177.60
m3
ESTRUCTUA DE BLOQUE DE GRADAS EN SEGUNDO PISO
313.42
1
HORMIGON SIMPLE f'c=210 kg/cm2 EN COLUMNAS
1.81
218.04
394.65
2
RIOSTRAS H. ARMADO ARMADURA ELECTROSOLDADA, SECCION 10x10, 4ø 7 mm, 1 mle ø 4 mm @ 0.15 m 4.00
9.54
38.16
3
RIOSTRAS H. ARMADO ARMADURA ELECTROSOLDADA, SECCION 15x10, 4ø 9 mm, 1 mle ø 5.5 mm @ 0.15 m 2.00
12.09
24.18
4
HORMIGON SIMPLE EN GRADAS f'c=210 kg/cm2
m3
3.62
182.16
659.42
5
HORMIGON SIMPLE EN LOSETA DE GRADAS f'c=210 kg/cm2
m3
0.64
182.16
116.58
6
BLOQUE DE POMEZ DE 0.15x0.20x0.40 m (EN LOSA)
u
45.00
0.47
21.15
7
HORMIGON SIMPLE EN VIGAS SUPERIORES f'c=210 kg/cm2
m3
2.52
220.73
556.24
8
ACERO DE REFUERZO f`y=4200 kg/cm2
kg
686.96
1.75
1,202.18
m2
33.02
11.56
MAMPOSTERIA 1
MAMPOSTERIA BLOQUE e= 15 cm
3,012.56
ENLUCIDOS
381.71 381.71
1
ENLUCIDO VERTICAL INT/EXT.
m2
68.91
9.24
636.73
2
ENLUCIDO DE CIELO RASO
m2
14.73
8.13
119.75
3
ENLUCIDO FILOS DE VIGAS
m
36.58
3.91
143.03
4
ENLUCIDO FILOS DE COLUMNAS
m
25.47
3.91
RECUBRIMIENTOS 1
PINTURA DE CAUCHO EXTERIOR
m2
83.01
3.77
m2
33.71
21.62
PISOS EN BLOQUES DE GRADAS 1
BALDOSA GRANITICA PARA PISOS (30x30) PULIDA
728.81 728.81
1
REJAS EN ESCALERA
m2
4.75
38.62
2
PASAMANOS DE MADERA DORMILON
ml
1.55
33.46
INSTALACIONES SANITARIAS BAJANTES DE AGUAS LLUVIAS
312.95 312.95
CARPINTERIA METAL / MADERA
1
99.59 999.10
183.45 51.86 235.31
ml
3.24
5.24
TERCER PISO
16.98 16.98
ESTRUCTURAS 1
HORMIGON SIMPLE f'c=210 kg/cm2 EN COLUMNAS
m3
11.34
218.04
2,472.57
2
HORMIGON SIMPLE EN LOSAS DE CUBIERTA f'c=210 kg/cm2
m3
27.82
203.82
5,670.27
3
BLOQUE DE POMEZ DE 0.15x0.20x0.40 m (EN LOSA)
u
2,248.00
0.47
1,056.56
4
RIOSTRAS H. ARMADO 15x10, BALCON
ml
40.33
15.68
632.37
5
RIOSTRAS H. ARMADO 15x10, EN PUERTAS Y VENTANAS
ml
161.20
12.09
1,948.91
6
HORMIGON SIMPLE EN VIGAS SUPERIORES f'c=210 kg/cm2
m3
24.28
220.73
5,359.32
7
MALLA ELECTROSOLDADA 15x15 ø 6 mm
m2
362.00
7.21
2,610.02
8
ACERO DE REFUERZO f`y=4200 kg/cm2
kg
5,580.00
1.75
MAMPOSTERIA
9,765.00 29,515.02
1
MAMPOSTERIA BLOQUE e= 15 cm
m2
235.45
11.56
2
MAMPOSTERIA BLOQUE e= 15 cm, EN BALCON
m2
20.62
11.58
ENLUCIDOS
2,721.80 238.78 2,960.58
1
ENLUCIDO VERTICAL INT/EXT.
m2
536.15
9.24
4,954.03
2
ENLUCIDO DE CIELO RASO
m2
310.05
8.13
2,520.71
3
ENLUCIDO VERTICAL DE BALCON
m2
41.24
9.24
381.06
4
ENLUCIDO FILOS DE PUERTAS Y VENTANAS
ml
161.20
2.29
369.15
5
ENLUCIDO FILOS DE VIGAS
m
137.00
3.91
535.67
6
ENLUCIDO FILOS DE COLUMNAS
m
233.28
3.91
912.12
7
ENLUCIDO DE LOSA DE CUBIERTA (IMPERMEABILIZACION)
m2
328.47
8.31
2,729.59
8
FORRADO DE BAJANTES AA. LL. CON MALLA NERVADA Y MORTERO 1:3
ml
73.00
4.90
357.70
9
GOTERO EN FACHADA PRINCIPAL
ml
40.00
3.87
RECUBRIMIENTOS
154.80 12,914.83
1
PINTURA DE CAUCHO INTERIOR
m2
628.34
3.54
2
PINTURA DE CAUCHO EXTERIOR
m2
259.10
3.77
PISOS EN TERCER PISO
2,224.32 976.81 3,201.13
1
BALDOSA GRANITICA PARA PISOS (30x30) PULIDA
m2
269.08
21.62
2
BARREDERA INTERIOR DE BALDOSA GRANITICA H=15 cm
ml
119.40
3.33
CARPINTERIA METAL / MADERA
5,817.51 397.60 6,215.11
1
CERRADURA LLAVE SEGURO-PUERTA EXTERIOR
u
4.00
15.02
60.08
2
PUERTA LAQUEADA DE DORMITORIO 0.90x2.10 SIN TARJETA
u
4.00
212.94
851.76
3
CONTRAVENTANAS DE HIERRO SEGÚN DISEÑO
m2
63.96
30.94
1,978.92
4
PASAMANOS DE MADERA DORMILON
ml
31.81
33.46
1,064.36
5
MANIGUETA DE BRONCE DE 4” EN PUERTAS
u
4.00
3.10
INSTALACIONES SANITARIAS
12.40 3,967.52
1
BAJANTES DE AGUAS LLUVIAS
ml
55.36
5.24
290.09
2
DESAGUES Y REJILLA DE PISO PVC /D; ø =75 mm
pto
8.00
22.20
177.60
ESTRUCTURA DE BLOQUE DE GRADAS EN TERCER PISO
467.69
1
HORMIGON SIMPLE f'c=210 kg/cm2 EN COLUMNAS
m3
1.36
218.04
296.53
2
HORMIGON SIMPLE EN LOSETA DE GRADAS f'c=210 kg/cm2
m3
2.30
182.16
418.97
3
BLOQUE DE POMEZ DE 0.15x0.20x0.40 m (EN LOSA)
188.00
0.47
88.36
4
HORMIGON SIMPLE EN VIGAS SUPERIORES f'c=210 kg/cm2
m3
2.26
220.73
498.85
5
MALLA ELECTROSOLDADA 15x15 ø 6 mm
m2
34.00
7.21
245.14
6
RIOSTRAS H. ARMADO ARMADURA ELECTROSOLDADA, SECCION 10x10, 4ø 7 mm, 1 mle ø 4 mm @ 0.15 m 2.00
9.54
19.08
7
RIOSTRAS H. ARMADO ARMADURA ELECTROSOLDADA, SECCION 15x10, 4ø 9 mm, 1 mle ø 5.5 mm @ 0.15 m 2.00
12.09
24.18
8
ACERO DE REFUERZO f`y=4200 kg/cm2
1,202.18
u
kg
686.96
1.75
m2
24.66
11.56
MAMPOSTERIA 1
MAMPOSTERIA BLOQUE e= 15 cm
2,793.29
ENLUCIDOS
285.07 285.07
1
ENLUCIDO VERTICAL INT/EXT.
m2
71.34
9.24
659.18
2
ENLUCIDO DE CIELO RASO
m2
34.87
8.13
283.49
3
ENLUCIDO FILOS DE VIGAS
m
29.41
3.91
114.99
4
ENLUCIDO FILOS DE COLUMNAS
m
16.53
3.91
64.63
5
ENLUCIDO DE LOSA DE CUBIERTA (IMPERMEABILIZACION)
m2
34.87
8.31
289.77
m2
106.21
3.77
RECUBRIMIENTOS 1
PINTURA DE CAUCHO EXTERIOR
1,412.06
CARPINTERIA METAL / MADERA
400.41 400.41
1
REJAS EN ESCALERA
m2
4.75
38.62
2
PASAMANOS DE MADERA DORMILON
ml
1.55
33.46
INSTALACIONES SANITARIAS
183.45 51.86 235.31
1
BAJANTES DE AGUAS LLUVIAS
ml
5.29
5.24
27.72
2
DESAGUES Y REJILLA DE PISO PVC /D; ø =75 mm
pto
1.00
22.20
22.20
54.00
30.40
1,641.60
INSTALACIONES ELECTRICAS
49.92
1
PUNTO DE ILUMINACION
pto
2
PUNTO DE TELEFONO
pto
5.00
23.21
116.05
3
LAMPARAS FLUORESCENTES 2x40 WATS , SIN ACRILICO SOBREPUESTA R/S
u
48.00
17.57
843.36
4
VENTILADOR DE TECHO
u
2.00
34.76
69.52
5
SECADOR DE MANOS 1000 W
u
2.00
152.76
305.52
6
PUNTO DE CONEXIÓN DE INTERNET
pto
3.00
63.93
191.79
7
PUNTO DE SECADOR DE MANOS
pto
2.00
26.43
52.86
8
PUNTO TOMACORRIENTE DOBLE POLARIZADO DE 110 V DE ENERGIA REGULADA pto
66.00
26.43
1,744.38
9
PUNTO TOMACORRIENTE DOBLE POLARIZADO DE 220 V DE ENERGIA REGULADA pto
5.00
28.66
143.30
10
CAJA DE BREAKER DE 8 PTOS, INCLUYE BREAKERS
u
6.00
88.16
528.96
11
ACOMETIDA ELECTRICA
m
20.00
44.89
897.80
12
TABLERO PRINCIPAL DE DISTRIBUCCION
u
1.00
456.52
ESTRUCTURAS
456.52 6,991.66
1
BORDILLO DE 0,20x0,50 f'c=180 kg/cm2
ml
104.32
14.69
1,532.46
2
PAVIMENTO DE ACERA INCLUYE REPLANTILLO DE PIEDRA BOLA e=10 cm
m2
92.72
20.27
1,879.43
3
TAPA JUNTA DE PISO, PARED Y CIELO RASO, EN ALUMINIO a=0.20 m
m
38.50
3.42
131.67
4
TAPA JUNTA DE LOSA DE CUBIERTA; CINTA CHOVA a=0.20 m
ml
7.50
3.34
OBRAS ESPECIALES 1
25.05 3,568.61
DESALOJO DE ESCOMBROS
m3
21.00
3.39
71.19 71.19
SUB-TOTAL =
$ 255,344.41
RESUMEN: NUMERO
VALOR UNIT
VALOR TOTAL
EDIFICIO C-2
DESCRIPCION
1
$ 255,344.41
$ 255,344.41
TALLER DE INDUSTRIA DEL ALIMENTO
1
$ 589,754.75
$ 589,754.75
EDUCACION INICIAL
3
$ 32,153.69
$ 96,461.07
OBRAS EXTERIORES
1
$ 11,243.48
$ 11,243.48
POZO ABSORVENTE
1
$ 1,009.07
$ 1,009.07
BATERIA SANITARIA 150 P
1
$ 12,696.42
$ 12,696.42
TOTAL=
$ 966,509.20
SON:
QUITO, 19 DE ABRIL DEL 2010
ABICEC CONSTRUCTORA CIA. LTDA OFERENTE
510,617.63
REFERENCIAL $1,097,948.86 $131,753.86 $966,195.00 0.880 0.120 12.00 $131,753.86 $966,195.00
12.00%
FORMULARIO No. 2 HOJA 1
DE 4
OBRA: CONSTRUCCION DE LA UNIDAD EDUCATIVA "SAN DANIEL COMBONI" UBICADA EN EL SITO Km. 8 VIA ESMERALDAS -ATACAMES UBICACIÓN: CANTON ATACAMES - PROVINCIA DE ESMERALDAS
CUADRO DE CANTIDADES Y PRECIOS RUBRO
DESCRIPCION
UNIDAD
CANTIDAD
P. UNITARIO
P. TOTAL
TALLER DE INDUSTRIA DEL ALIMENTO 1 PRELIMINARES 2 REPLANTEO Y NIVELACION
m2
1,690.45
0.83
1 EXCAVACION PARA REALIZAR CAMBIO DE SUELO A MAQUINA
m3
2,535.67
2.33
2 EXCAVACION DE CIMIENTOS CON MAQUINARIA
m3
104.69
2.33
243.93
2,376.42
32.20
76,520.72 6,942.06
MOVIMIENTOS DE TIERRAS
1,403.07 1,403.07
3 CAMBIO DE SUELO CON MATERIAL SELECCIONADOI, (CASCOTE AMARILLO NO PLASTICO) m3 4 RELLENO CON LASTRE COMPACTADO EN PLINTOS Y CONTRAPISO H=0,30 m
m3
504.51
13.76
5 DESALOJO DE MATERIAL
m3
2,640.36
3.39
ESTRUCTURA EN CIMENTACION
5,908.11
8,950.82 98,565.64
1 REPLANTILLOS H.S. f'c=140 kg/cm2
m2
232.62
7.39
2 REPLANTILLO DE PIEDRA BOLA e=10 cm
m2
232.62
5.47
1,272.43
3 HORMIGON SIMPLE EN PLINTOS f'c=210 kg/cm2
m3
159.26
145.84
23,226.48
4 MURO DE HORMIGON CICLOPEO f'c=180 kg/cm2
m3
59.14
93.55
5,532.55
5 HORMIGON SIMPLE EN CADENAS INFERIORES f'c=210 kg/cm2
m3
36.34
178.95
6,503.04
6 ACERO DE REFUERZO f`y=4200 kg/cm2
kg
6,246.43
1.75
10,931.25
1,449.09
19.69
ESTRUCTURAS
1,719.06
49,184.81
1 HORMIGON SIMPLE EN CONTRAPISO H.S. e=10 cm f'c=180 kg/cm2 INC. MALLA ELECTROSOLDADA m2
28,532.58
2 HORMIGON SIMPLE f'c=210 kg/cm2 EN COLUMNAS
m3
31.11
218.04
6,783.22
3 HORMIGON SIMPLE EN LOSAS DE ENTREPISO f'c=210 kg/cm2
m3
49.57
203.82
10,103.36
4 BLOQUE DE POMEZ DE 0.15x0.20x0.40 m (EN LOSA)
u
4,066.00
0.47
1,911.02
5 RIOSTRAS H. ARMADO 15x10, EN PUERTAS Y VENTANAS
ml
273.29
12.09
3,304.08
6 VIGA ELECTROSOLDADA SECC. 0.10x0.10 m 4ø 7 mm, 1 e ø 4 mm @ 0.15 m
m
273.29
5.02
1,371.92
7 HORMIGON SIMPLE EN VIGAS SUPERIORES f'c=210 kg/cm2
m3
59.34
220.73
13,098.12
8 HORMIGON SIMPLE EN GRADAS f'c=210 kg/cm2
m3
5.82
182.16
1,060.17
9 ACERO DE REFUERZO f`y=4200 kg/cm2
kg
16,223.97
1.75
28,391.95
1 MAMPOSTERIA BLOQUE e= 15 cm
m2
731.67
11.56
2 MESON PARA LAVAMANOS, COCINA Y LABORATORIO INCLUYE CERAMICA
m2
20.88
41.54
MAMPOSTERIA
94,556.42
ENLUCIDOS
8,458.11 867.36 9,325.47
1 ENLUCIDO VERTICAL INT/EXT.
m2
1,697.33
9.24
15,683.33
2 ENLUCIDO DE CIELO RASO
m2
655.20
8.13
5,326.78
3 ENLUCIDO FILOS DE PUERTAS Y VENTANAS
ml
305.00
2.29
698.45
4 ENLUCIDO FILOS DE VIGAS
m
721.00
3.91
2,819.11
5 ENLUCIDO FILOS DE COLUMNAS
m
725.04
3.91
RECUBRIMIENTOS
2,834.91 27,362.58
1 PINTURA DE CAUCHO INTERIOR
m2
1,411.63
3.54
4,997.17
2 PINTURA DE CAUCHO EXTERIOR
m2
941.10
3.77
3,547.95
3 CERAMICA PARA PARED
m2
158.56
18.90
PISOS EN PLANTA BAJA
2,996.78 11,541.90
1 MASILLADO DE PISOS
m2
410.35
6.32
2,593.41
2 CERAMICA DE PISO 0.40x0.40 m
m2
410.35
15.98
6,557.39
3 BARREDERA DE CERAMICA H=10 cm
m
108.28
3.49
377.90
4 PISO INDUSTRIAL SISTEMA SIKAFLOR
m2
608.90
8.43
5,133.03
1 CERRADURA LLAVE SEGURO-PUERTA EXTERIOR
u
22.00
15.02
2 CERRADURAS DE POMO
u
19.00
12.66
240.54
3 PUERTA LAQUEADA DE DORMITORIO 1.00x2.10 SIN TARJETA
u
20.00
224.74
4,494.80
4 PUERTA DE ALUMINIO BLANCO 0.70x2.10 m
u
19.00
172.00
3,268.00
5 PUERTA LAQUEADA DE DORMITORIO 0.90x2.10 SIN TARJETA
u
4.00
212.94
851.76
6 PUERTA METALICA TIPO LANFORD, CON PLACAS LISAS ACERO GALVANIZADO PINTURA m2 ANTICORROSIVA 41.25
86.62
3,573.08
7 VENTANA DE ALUMINIO CON VIDRIO TRANSPARENTE e= 4 mm
m2
50.00
66.73
3,336.50
8 CONTRAVENTANAS DE HIERRO SEGÚN DISEÑO
m2
26.70
30.94
826.10
CARPINTERIA METAL / MADERA
14,661.73 330.44
9 MANIGUETA DE BRONCE DE 4” EN PUERTAS
u
22.00
3.10
INSTALACIONES SANITARIAS
68.20 16,989.42
1 SALIDA DE AGUA POTABLE 1/2"
pto
30.00
17.64
529.20
2 DESAGUES Y REJILLA DE PISO ø =110 mm
pto
8.00
25.13
201.04
3 LAVADERO DE ACERO INOXIDABLE DE DOBLE POZO
u
5.00
158.32
791.60
4 ACOMETIDA DE AGUA POTABLE
ml
42.00
2.98
125.16
5 LLAVE DE PASO Y CONTROL
u
24.00
9.89
237.36
6 BAJANTES DE AGUAS LLUVIAS ø 110 mm
ml
30.56
5.24
160.13
7 CAJAS DE REVISION EXTERIOR DE 0,60x0,60x0.80 CON TAPA
u
16.00
76.92
1,230.72
8 INODORO TANQUE BAJO COLOR BLANCO
u
4.00
95.22
380.88
9 LAVAMANOS
u
6.00
59.45
356.70
10 DUCHAS
u
4.00
14.25
57.00
11 URINARIO DE COLOR BLANCO
u
2.00
152.33
304.66
12 TAPA CON REJILLA DE H.A. 0.60x0.30 m
m
30.40
44.00
1,337.60
PLANTA ALTA
5,712.05
ESTRUCTURAS 1 HORMIGON SIMPLE f'c=210 kg/cm2 EN COLUMNAS
m3
31.11
218.04
6,783.22
2 HORMIGON SIMPLE EN LOSAS DE CUBIERTA f'c=210 kg/cm2
m3
52.61
203.82
10,722.97
0.47
2,010.19
11.96
3,677.82
3 BLOQUE DE POMEZ DE 0.15x0.20x0.40 m (EN LOSA)
u
4,277.00
4 RIOSTRA H. A., CON MEDIA ARMADURA ELECTROSOLDADA, SECCION 25X15cm, 2 Øml12 mm, 1 e Ø 6 mm 307.51 @ 0,15 m 5 VIGA ELECTROSOLDADA SECC. 0.10x0.10 m 4ø 7 mm, 1 e ø 4 mm @ 0.15 m
m
307.51
5.02
1,543.70
6 HORMIGON SIMPLE EN VIGAS SUPERIORES f'c=210 kg/cm2
m3
59.54
220.73
13,142.26
7 MALLA ELECTROSOLDADA ø 4.5 mm 15x15
m2
618.65
4.48
MAMPOSTERIA
2,771.55 40,651.71
1 MAMPOSTERIA BLOQUE e= 15 cm
m2
666.60
11.56
2 MESON PARA LAVAMANOS INCLUYE CERAMICA
m2
12.00
41.54
ENLUCIDOS
7,705.90 498.48 8,204.38
1 ENLUCIDO VERTICAL INT/EXT.
m2
1,617.00
9.24
14,941.08
2 ENLUCIDO DE CIELO RASO
m2
690.07
8.13
5,610.27
3 ENLUCIDO FILOS DE PUERTAS Y VENTANAS
ml
171.45
2.29
392.62
4 ENLUCIDO FILOS DE VIGAS
m
735.00
3.91
2,873.85
5 ENLUCIDO FILOS DE COLUMNAS
m
657.20
3.91
2,569.65
6 ENLUCIDO DE LOSA DE CUBIERTA (IMPERMEABILIZACION)
m2
618.65
8.31
RECUBRIMIENTOS
5,140.98 31,528.45
1 PINTURA DE CAUCHO INTERIOR
m2
1,669.77
3.54
5,910.99
2 PINTURA DE CAUCHO EXTERIOR
m2
555.60
3.77
2,094.61
3 CERAMICA PARA PARED
m2
121.00
18.90
PISOS
2,286.90 10,292.50
1 CERAMICA DE PISO 0.40x0.40 m
m2
555.48
15.98
2 BARREDERA DE CERAMICA H=10 cm
m
341.27
3.49
CARPINTERIA METAL / MADERA
8,876.57 1,191.03 10,067.60
1 CERRADURA LLAVE SEGURO-PUERTA EXTERIOR
u
13.00
15.02
2 CERRADURAS DE POMO
u
12.00
12.66
151.92
3 PUERTA LAQUEADA DE DORMITORIO 1.00x2.10 SIN TARJETA
u
11.00
224.74
2,472.14
4 PUERTA DE ALUMINIO BLANCO 0.70x2.10 m
u
12.00
172.00
2,064.00
5 PUERTA LAQUEADA DE DORMITORIO 0.90x2.10 SIN TARJETA
u
4.00
212.94
851.76
m2
106.00
66.73
7,073.38
u
15.00
3.10
6 VENTANA DE ALUMINIO CON VIDRIO TRANSPARENTE e= 4 mm 7 MANIGUETA DE BRONCE DE 4” EN PUERTAS INSTALACIONES SANITARIAS 1 SALIDA DE AGUA POTABLE 1/2"
195.26
46.50 12,854.96
pto
20.00
17.64
352.80
2 LLAVE DE PASO Y CONTROL
u
20.00
9.89
197.80
3 INODORO TANQUE BAJO COLOR BLANCO
u
4.00
95.22
380.88
4 LAVAMANOS
u
6.00
59.45
356.70
5 DUCHAS
u
4.00
14.25
57.00
6 URINARIO DE COLOR BLANCO
u
2.00
152.33
304.66
7 LAVAPLATOS DE ACERO INOXIDABLE UN POZO CON LLAVE Y HERRAJES
u
2.00
99.32
198.64
8 LAVAPLATOS DE ACERO INOXIDABLE DOS POZOS CON LLAVE Y HERRAJES
u
1.00
158.32
158.32
9 BAJANTES DE AGUAS LLUVIAS ø 110 mm
ml
24.80
5.24
129.95
pto
6.00
22.20
133.20
11 CANOERA DE HIERRO Y TOL 1/20" PARA AGUAS LLUVIAS, INC. SOPORTES PLATINAml1"x1/4"
34.00
10.22
347.48
12 PASAMANO DE TUBO CON MANGO DE MADERA
m
61.11
62.34
3,809.60
13 VISERA DE HORMIGON SIMPLE INC. MALLA 4x15x15
m3
1.20
240.40
288.48
10 DESAGUES Y REJILLA DE PISO PVC /D; ø =75 mm
ESTRUCTURA Y CUBIERTA METALICA
6,715.51
1 SUM. / INST. DE CORREAS TIPO C Y G, CERCHAS Y ANGULOS METALICOS SEGÚN SE kg ESPECIFICA 7,218.43
3.15
22,738.05 12,894.60
2 SUMINISTRO E INSTALACION DE CUBIERTA TIPO ESTIL AR-2 e=0.40 mm
m2
874.21
14.75
3 SUMINISTRO E INSTALACION DE FRISO RECTO PREPINTADO
m2
50.28
20.61
RED DE ALCANTARILLADO DE AGUAS SERVIDAS
1,036.27 36,668.92
1 REPLANTEO Y NIVELACION
ml
139.50
0.22
30.69
2 EXCAVACION A MAQUINA
m3
186.37
1.77
329.87
3 RESANTEO MANUAL
m
139.50
0.55
76.73
4 CAMA DE ARENA e=10 cm
ml
139.50
4.57
637.52
5 SUM. / INST. DE TUBERIA PVC/D ø 200 mm
ml
139.50
9.98
1,392.21
6 RELLENO Y COMPACTACION CON SUELO NATURAL
m3
181.99
3.71
675.18
7 DESALOJO
m3
15.54
3.39
POZOS DE INSPECCION
52.68 3,194.88
1 EXCAVACION MANUAL PARA POZOS
m3
32.79
3.11
2 RELLENO Y COMPACTACION CON SUELO NATURAL
m3
23.91
3.71
88.71
3 POZOS DE H.A. ø INT=90 cm, H=1.00 a 2.50 m INC. ENCOFRADO, TAPA Y ESCALERA u
4.00
388.60
1,554.40
4 DESALOJO
8.88
3.39
m3
INSTALACIONES ELECTRICAS
101.98
30.10 1,775.19
1 PUNTO ILUMINACION 110 V
pto
148.00
30.40
2 PUNTO ILUMINACION 220 V
pto
18.00
34.61
4,499.20 622.98
3 PROVISION E INSTALACION DE LUMINARIA 2x32 W TIPO INDUSTRIAL
u
30.00
44.09
1,322.70
4 PROVISION E INSTALACION DE LUMINARIA 3x32 W TIPO INDUSTRIAL
u
48.00
55.89
2,682.72
5 PLAFON DE PORCELANA
u
46.00
1.97
90.62
6 LUMINARIA 3x17 W
u
24.00
31.11
746.64
7 LUMINARIA 250 W
u
18.00
146.52
2,637.36
8 PUNTO TOMACORRIENTE DOBLE POLARIZADO DE 110 V DE ENERGIA REGULADA pto
108.00
26.43
2,854.44
9 PUNTO TOMACORRIENTE DOBLE POLARIZADO DE 220 V DE ENERGIA REGULADA pto
10.00
28.66
TABLEROS
286.60 15,743.26
1 CENTRO DE CARGA 24 PUNTOS, INCLUYE BREAKERS
u
3.00
252.72
758.16
2 TABLEROS LINEAS DE PRODUCCION 0.70x0.40x0.90 m COMPLETO
u
3.00
209.56
628.68
3 TABLERO GENERAL 1.30x0.40x1.80m COMPLETO
u
1.00
659.14
ACOMETIDAS
659.14 2,045.98
1 ACOMETIDA PRINCIPAL (4 LINEAS), CONDUCTOR No. 500 mcm
ml
168.00
227.35
38,194.80
2 ACOMETIDA T-G/T-L,T-E,T-F (3 LINEAS) FASE AWG-TTU # 1
ml
120.00
30.24
3,628.80
3 ACOMETIDA T-G/T-L,T-E,T-F (1 LINEA) NEUTRO AWG-TTU # 2
ml
40.00
5.24
209.60
4 ACOMETIDA T-G/T-L,T-E,T-F TIERRA AWG-TTU # 4
ml
40.00
3.81
152.40
5 ACOMETIDA T-G/T-3, FASE No. 2 AWG-TTU
ml
90.00
14.14
1,272.60
6 ACOMETIDA T-G/T-3, NEUTRO No. 4 AWG-TTU
ml
30.00
9.85
295.50
7 ACOMETIDA T-G/T-3, TIERRA No. 6 AWG-TTU
ml
30.00
6.99
209.70
8 ACOMETIDA T-G/T-1, F. No. 2
ml
186.00
5.24
974.64
9 ACOMETIDA T-G/T-1, F. No. 4
ml
62.00
3.81
236.22
10 ACOMETIDA T-G/T-1, F. No. 6
ml
62.00
2.86
177.32
11 ACOMETIDA T-G/T-2, F. No. 2 AWG-TTU
ml
201.00
9.69
1,947.69
12 ACOMETIDA T-G/T-2, N. No. 4
ml
67.00
6.83
457.61
13 ACOMETIDA T-G/T-2, T. No. 6
ml
67.00
4.92
329.64
14 TUBERIA PVC/D ø 4" ACOMETIDA TRANSFORMADOR A GENERAL
ml
80.00
11.02
881.60
15 TUBERIA PVC/D ø 3" ACOMETIDA GENERAL AL T-L,T-E,T-F,T-1,T-2Y T-3
ml
240.00
7.40
1,776.00
OBRAS EXTERIORES
50,744.12
ESTRUCTURAS 1 BORDILLO DE 0,15x0,50 f'c=180 kg/cm2
165.10
11.87
1,959.74
2 ACERAS H.S. F'c=180 kg/cm2, e=8 cm inc.replantillo piedra bola 14 cm y malla electrosoldada m2 10x10 ø 4 mm 221.95
ml
20.27
4,498.93
OBRAS ADICIONALES 1 DESALOJO DE MATERIAL
6,458.67 m3
25.60
3.39
OBRAS EXTERIORES
86.78 86.78
OBRAS PRELIMINARES 1 REPLANTEO Y NIVELACION
m2
69.66
0.83
57.82
1 EXCAVACION A MAQUINA
m3
111.46
1.77
197.28
2 DESALOJO DE MATERIAL
m3
111.46
3.39
377.85
1 REPLANTILLOS H.S. f'c=140 kg/cm2 e=5 cm
m2
69.66
7.39
514.79
2 REPLANTILLO DE PIEDRA BOLA e=10 cm
m2
69.66
5.47
381.04
MOVIMIENTOS DE TIERRAS
57.82
ESTRUCTURA EN CIMENTACION
575.13
ESTRUCTURAS 1 HORMIGON SIMPLE f'c=210 kg/cm2 EN CISTERNA
895.83 m3
52.17
174.67
9,112.53
2 VIGA ELECTROSOLDADA SECC. 0.15x0.15 m 4ø127 mm, 1 e ø 6 mm @ 0.15 m
m
18.66
6.68
124.65
3 ACERO DE REFUERZO f`y=4200 kg/cm2
kg
3,617.92
1.75
6,331.36
1 ENLUCIDO HORIZONTAL MORTERO 1:3 + SIKA
m2
59.52
9.73
579.13
2 ENLUCIDO VERTICAL MORTERO 1:3 + SIKA
m2
120.57
8.08
974.21
3 ENLUCIDO DE FILOS
ml
13.20
2.29
ENLUCIDOS
15,568.54
METAL 1 SUMINISTRO E INSTALACION DE TAPA SANITARIA
30.23 1,583.57
u
1.00
44.17
44.17
1 SUM/INST. TUBERIA DE H.G. Ø 2”, + PRUEBA
ml
4.10
18.23
2 SUM/INST. UNION UNIVERSAL H.G. Ø 3/4”, + PRUEBA
u
2.00
2.20
4.40
3 SUM/INST. UNION UNIVERSAL H.G. Ø 2”, + PRUEBA
u
6.00
6.10
36.60
4 SUM/INST. VALVULA PVC DE PIE CON REJILLA 2” + PRUEBA
u
SISTEMA DE BOMBEO
44.17 74.74
1.00
13.34
13.34
5 SUM/INST. VALVULA DE COMPUERTA Y VOLANTE (BRONCE RW) ø=3/4” E/R + PRUEBA u
1.00
14.27
14.27
6 SUM/INST. VALVULA DE COMPUERTA Y VOLANTE (BRONCE RW) ø=2” E/R + PRUEBAu
2.00
28.54
57.08
7 SUM/INST. VALVULA DE COMPUERTA Y CUADRO (BRONCE RW) ø=3/4” E/R + PRUEBA u
1.00
19.04
19.04
8 SUM/INST. VALVULA CHECK (BRONCE RW) ø=2” E/R + PRUEBA
u
1.00
54.71
54.71
9 SUM/INST. UNION GIBAULT ø=110 mm, E/L + PRUEBA
u
2.00
45.82
91.64
10 SUM/INST CODO PVC-P d=110 mm x 90º E/C
u
2.00
6.61
13.22
11 SUM/INST. DE TUBERIA PVC/D d=110 mm
ml
48.35
6.04
292.03
12 VALVULA DE COMPUERTA TIPO CUADRO d=110 mm
u
1.00
209.56
209.56
13 SUMINSTRO E INSTALACION DE BOMBA DE 3 HP
u
1.00
775.96
775.96
14 SUMINSTRO E INSTALACION DE TANQUE HIDRONEUMATICO DE 200 GALONES
u
1.00
1,123.41
1,123.41
15 SUMINSTRO E INSTALACION DE ACCEOSRIOS VARIOS PARA EL FUNCIONAMIENTO global SISTEMA BOMBEO 1.00
1,898.43
1,898.43
OBRAS ADICIONALES 1 DESALOJO DE ESCOMBROS
4,678.43 m3
4.50
3.39
15.26 15.26
SUB-TOTAL =
QUITO, 19 DE ABRIL DEL 2010
$ 589,754.75
ABICEC CONSTRUCTORA CIA. LTDA OFERENTE
1,179,509.50
FORMULARIO No. 2 HOJA 1
DE 2
OBRA: CONSTRUCCION DE LA UNIDAD EDUCATIVA "SAN DANIEL COMBONI" UBICADA EN EL SITO Km. 8 VIA ESMERALDAS -ATACAMES UBICACIÓN: CANTON ATACAMES - PROVINCIA DE ESMERALDAS
CUADRO DE CANTIDADES Y PRECIOS RUBRO
DESCRIPCION
UNIDAD
CANTIDAD
P. UNITARIO
P. TOTAL
EDUCACION INICIAL 1 PRELIMINARES 2 LIMPIEZA DEL TERRENO
m2
213.13
0.47
100.17
3 REPLANTEO
m2
213.13
1.40
298.38
1 DESALOJO DE CIMIENTOS - VOLQUETA
m3
5.48
3.18
17.43
2 EXCAVACION DE CIMIENTOS
m3
23.56
5.42
127.70
3 RELLENO EN CIMIENTO CON MATERIAL – EXCAVACION
m3
18.08
3.86
MOVIMIENTOS DE TIERRAS
398.55
CIMIENTOS
69.79 214.92
1 HORMIGON SIMPLE EN PLINTOS – COSTA
m3
3.97
145.84
578.98
2 HORMIGON SIMPLE EN REPLANTILLOS
m3
0.92
118.43
108.96
3 RELLENO DE PIEDRA BOLA
m3
9.50
32.44
308.18
932.00
0.42
391.44 513.59
ESTRUCTURA 1 ALIVIANAMIENTO DE BLOQUE 40x20x10
996.12 u
2 HORMIGON EN CADENAS H.S.
m3
2.87
178.95
3 HORMIGON EN COLUMNAS
m3
3.22
218.04
702.09
4 LOSA DE CUBIERTA
m3
19.06
203.82
3,884.81
5 RIOSTRA DE 15x15 cm H.A.
ml
19.80
20.29
401.74
6 ACERO DE REFUERZO
kg
2,944.77
1.75
5,153.35
1 MAMPOSTERIA BLOQUE-CEM-ARENA 10 cm
m2
6.48
9.96
64.54
2 MAMPOSTERIA BLOQUE-CEM-ARENA 15 cm
m2
95.74
11.56
1,106.75
m2
98.87
11.78
m2
107.13
17.41
m2
390.36
9.63
1 AZULEJO O CERAMICA DE PARED
m2
29.22
18.73
2 BARREDERA DE CERAMICA
m
27.60
3.54
MAMPOSTERIA
11,047.02
CONTRAPISOS 1 CONTRAPISO TIPO COSTA (INCLUYE MALLA ELECTROSOLDADA)
1,171.29
PISOS 1 CERAMICA ALTO TRAFICO
1,164.69
ENLUCIDOS 1 ENLUCIDO LISO ESTUCADO
1,865.13 1,865.13
REVESTIMIENTOS
3,759.17 3,759.17
CARPINTERIA 1 PUERTAS MADERA (ADAS -CON TARJETA)
1,164.69
547.29 97.70 644.99
m2
8.80
171.85
3 REJAS DE TUBO MECANICO CUADRADO
m2
44.28
47.25
2,092.23
4 VENTANA DE ALUMINIO Y VIDRIO ESMERALDAS
m2
33.00
62.40
2,059.20
1 CAJAS DE REVISION C/TAPA
u
3.00
58.81
176.43
2 SUMIDERO 50 mm CON TRAMPA
u
6.00
11.07
66.42
3 TUBERIA PVC DE 10 cm
ml
19.10
4.84
2 HERRERIA
1,512.28
CANALIZACION
4,151.43
AGUAS LLUVIAS 1 BAJANTE PVC DE 10 cm
1,512.28
92.44 335.29
ml
15.00
5.64
84.60
1 DESAGUES DE AGUAS NEGRAS 4”
pto
7.00
15.38
107.66
2 DESAGUES DE AGUAS NEGRAS 2”
pto
6.00
10.66
DESAGUE DE AGUAS NEGRAS
84.60
MUEBLES SANITARIOS
63.96 171.62
1 INODORO TANQUE BAJO
u
2.00
95.22
190.44
2 LAVAMANOS COLECTIVO
ml
4.15
51.76
214.80
3 DUCHA CROMADA
u
2.00
13.41
26.82
4 LAVAMANOS
u
2.00
59.45
118.90
u
14.00
9.73
136.22
2 PUNTO SALIDA AGUA POTABLE
pto
16.00
17.64
282.24
3 TUBERIA PVC PRESION 1/2”
ml
10.00
1.82
18.20
AGUA POTABLE 1 LLAVE DE AA. PP. D=1/2”
550.96
INSTALACION ELECTRICA 1 VOZ Y DATOS 2 PROVISION E INSTALACION DE LUMINARIAS 2x32 WATS TIPO INDUSTRIAL 3 PUNTO DE ILUMINACION 4 TABLERO DE CONTROL 4 BREAKERS 5 TOMACORRIENTE DOBLE
436.66 pto
6.00
80.07
480.42
u
16.00
44.33
709.28
pto
18.00
30.40
547.20
u
2.00
67.86
135.72
pto
8.00
26.43
PINTURA
211.44 2,084.06
1 PINTURA CIELO RASO
m2
175.54
4.10
2 PINTURA DE CAUCHO
m2
185.60
3.55
VARIOS
719.71 658.88 1,378.59
1 BORDILLO HORMIGON SIMPLE 30x10 cm
ml
1.95
7.41
14.45
2 ROTULO METALICO REFORZ 1,22x2,44
u
1.00
171.87
171.87 186.32
SUB-TOTAL =
QUITO, 19 DE ABRIL DEL 2010
$ 32,153.69
ABICEC CONSTRUCTORA CIA. LTDA OFERENTE
55,466.26
556.44
FORMULARIO No. 2 HOJA 1
DE 1
OBRA: CONSTRUCCION DE LA UNIDAD EDUCATIVA "SAN DANIEL COMBONI" UBICADA EN EL SITO Km. 8 VIA ESMERALDAS -ATACAMES UBICACIÓN: CANTON ATACAMES - PROVINCIA DE ESMERALDAS
CUADRO DE CANTIDADES Y PRECIOS RUBRO
DESCRIPCION
UNIDAD
CANTIDAD
P. UNITARIO
P. TOTAL
OBRAS EXTERIORES 1 PRELIMINARES 2 LIMPIEZA DEL TERRENO
m2
132.00
0.47
62.04
1 EXCAVACION DE CIMIENTOS
m3
26.40
5.42
143.09
2 DESALOJO DE CIMIENTOS - VOLQUETA
m3
31.68
3.18
100.74
3 CONFORMACION DE PLATAFORMAS CON MATERIAL IMPORTADO
m3
26.40
4.76
125.66
1 ADOQUIN ECOLOGICO
m2
132.00
10.99
1,450.68
2 BORDILLO HORMIGON SIMPLE 30x10 cm
ml
40.00
7.41
296.40
3 TUBERIA PVC DE 10 cm
ml
50.00
4.84
242.00
4 ENCESPADO Y ARREGLO DE JARDINES
m2
120.00
5.37
644.40
MOVIMIENTOS DE TIERRAS
VARIOS
INSTALACIONES ELECTRICAS 1 LUMINARIA FLUORESCENTE DE 1x32 W DE SOBREPONER
u
5.00
21.91
109.55
2 LUMINARIA 150 W MH
u
1.00
148.35
148.35
3 PUNTO DE LUZ
pto
9.00
27.67
249.03
4 CUBIERTA DE PATIO (ESTRUCTURA Y TECHO ALVEOLAR)
m2
147.70
51.94
7,671.54
SUB-TOTAL =
QUITO, 19 DE ABRIL DEL 2010
$ 11,243.48
ABICEC CONSTRUCTORA CIA. LTDA OFERENTE
11,243.48
FORMULARIO No. 2 HOJA 1
DE 1
OBRA: CONSTRUCCION DE LA UNIDAD EDUCATIVA "SAN DANIEL COMBONI" UBICADA EN EL SITO Km. 8 VIA ESMERALDAS -ATACAMES UBICACIÓN: CANTON ATACAMES - PROVINCIA DE ESMERALDAS
CUADRO DE CANTIDADES Y PRECIOS RUBRO
DESCRIPCION
UNIDAD
CANTIDAD
P. UNITARIO
P. TOTAL
POZO ABSORVENTE 1
PRELIMINARES
2
LIMPIEZA DEL TERRENO
m2
18.50
0.47
8.70
3
REPLANTEO
m2
5.31
1.40
7.43
MOVIMIENTOS DE TIERRAS 1
DESALOJO DE CIMIENTOS CON CARRETILLA
m3
22.00
5.26
115.72
2
EXCAVACION DE CIMIENTOS
m3
18.50
5.42
100.27
kg
65.22
1.75
114.14
ESTRUCTURA 1
ACERO DE REFUERZO POZO ABSORVENTE
1
GRAVA PARA SEDIMENTACION
m3
0.50
27.89
13.95
2
HORMIGON SIMPLE PARA POZO ABSORVENTE
m3
1.20
145.84
175.01
3
MAMPOSTERIA DE LADRILLO SIN MASILLA
m2
22.00
14.63
321.86
ml
3.00
13.65
40.95
u
6.20
FOSA SEPTICA 1
DUCTO VENTILACION H.G. d=5 cm TANQUE CISTERNA
1
TAPA H.A. PARA e=10 cm 50x50 CISTERNA
17.91 SUB-TOTAL =
QUITO, 19 DE ABRIL DEL 2010
111.04 $ 1,009.07
ABICEC CONSTRUCTORA CIA. LTDA OFERENTE
1,009.07
FORMULARIO No. 2 HOJA 1
DE 2
OBRA: CONSTRUCCION DE LA UNIDAD EDUCATIVA "SAN DANIEL COMBONI" UBICADA EN EL SITO Km. 8 VIA ESMERALDAS -ATACAMES UBICACIÓN: CANTON ATACAMES - PROVINCIA DE ESMERALDAS
CUADRO DE CANTIDADES Y PRECIOS RUBRO
DESCRIPCION
UNIDAD
CANTIDAD
P. UNITARIO
P. TOTAL
BATERIA SANITARIA 150 P 1 PRELIMINARES 2 LIMPIEZA DEL TERRENO
m2
61.20
0.47
28.76
3 REPLANTEO
m2
16.43
1.40
23.00
MOVIMIENTOS DE TIERRAS 1 DESALOJO DE CIMIENTOS - VOLQUETA
m3
7.81
3.18
24.84
2 REPOSICION DE SUELO
m3
12.20
42.89
523.26
3 EXCAVACION DE CIMIENTOS
m3
12.33
5.42
66.83
4 RELLENO EN CIMIENTO CON MATERIAL – EXCAVACION
m3
4.52
3.86
17.45
1 HORMIGON SIMPLE EN ZAPATAS
m3
3.39
131.76
446.67
2 HORMIGON SIMPLE EN REPLANTILLOS
m3
0.65
118.43
76.98
78.66
CIMIENTOS
ESTRUCTURA 1 ALIVIANAMIENTO DE BLOQUE 40x20x15
171.00
0.46
2 HORMIGON EN CADENAS H.S.
m3
u
0.51
178.95
91.26
3 HORMIGON EN COLUMNAS
m3
0.82
218.04
178.79
4 HORMIGON EN VIGAS
m3
1.49
220.73
328.89
5 LOSA DE CUBIERTA
m3
3.10
203.82
631.84
6 RIOSTRA DE 10x10 cm
ml
9.12
10.16
92.66
7 RIOSTRA DE 10x15 cm
ml
24.42
13.11
320.15
8 ACERO DE REFUERZO
kg
950.20
1.75
1,662.85
1 MAMPOSTERIA BLOQUE-CEM-ARENA 10 cm
m2
29.70
9.96
295.81
2 MAMPOSTERIA BLOQUE-CEM-ARENA 15 cm
m2
37.78
11.56
436.74
1 CONTRAPISO TIPO COSTA (INCLUYE MALLA ELECTROSOLDADA)
m2
13.42
11.78
158.09
2 MALLA ELECTROSOLDADA R-64
m2
33.90
2.94
99.67
m2
13.42
17.41
233.64
1 ENLUCIDO LISO ESTUCADO
m2
149.22
9.63
1,436.99
2 ENLUCIDO PALETEADO
m2
33.66
6.36
214.08
3 MEDIAS CAÑAS
m
46.52
0.62
28.84
m2
33.90
8.36
283.40
m2
33.66
18.73
630.45
1 CANDADOS VIRO 50 mm
u
2.00
7.81
15.62
2 CERRADURA LLAVE – LLAVE
u
3.00
16.41
49.23
3 PICAPORTES
u
3.00
1.91
5.73
4 TIRADERA NIQUELADA 5"
u
3.00
3.38
10.14
1 PUERTA METALIC-TOL REJAS
m2
4.68
109.75
513.63
2 PUERTA DE TOL C/MARCO
m2
5.42
74.24
402.38
3 REJAS TIPO
m2
8.70
43.96
382.45
1 CAJAS DE REVISION C/TAPA
u
2.00
58.81
117.62
2 SUMIDERO 50 mm CON TRAMPA
u
3.00
11.07
33.21
3 TUBERIA PVC DE 10 cm
ml
10.00
4.84
48.40
1 REJILLA INCLUYE SIFON
u
1.00
5.47
5.47
2 BAJANTE PVC DE 10 cm
ml
4.24
5.64
23.91
MAMPOSTERIA
CONTRAPISOS
PISOS 1 CERAMICA ALTO TRAFICO ENLUCIDOS
IMPERMEABILIZACION Y PENDIENTES 1 IMPERMEABILIZACION Y PENDIENTES REVESTIMIENTOS 1 AZULEJO O CERAMICA DE PARED CERRAJERIA
HERRERIA
CANALIZACION
AGUAS LLUVIAS
DESAGUE DE AGUAS NEGRAS
1 DESAGUES DE AGUAS NEGRAS 4”
pto
4.00
15.38
61.52
2 DESAGUES DE AGUAS NEGRAS 2”
pto
2.00
10.66
21.32
1 INODORO TANQUE BAJO
u
4.00
95.22
380.88
2 LAVAMANOS COLECTIVO
ml
2.05
51.76
106.11
3 URINARIO COLECTIVO
ml
1.17
28.80
33.70
4 LAVAMANOS
u
2.00
59.45
118.90
MUEBLES SANITARIOS
AGUA POTABLE 1 LLAVE DE MANGUERA
u
5.00
6.33
31.65
2 PUNTO SALIDA AGUA POTABLE
pto
11.00
17.64
194.04
3 TUBERIA HIDRO 3 ( 1/2”)
ml
15.00
1.57
23.55
1 ACOMETIDA ELECTRICA No. 10
m
15.00
3.76
56.40
2 FOCOS
u
7.00
3.23
22.61
pto
7.00
30.40
212.80
u
1.00
43.48
43.48
INSTALACION ELECTRICA
3 PUNTO DE ILUMINACION 4 TABLERO DE CONTROL 2 BREAKERS PINTURA 1 PINTURA CIELO RASO
m2
33.93
4.10
139.11
2 PINTURA DE CAUCHO
m2
149.22
3.55
529.73
1 S PAV.C/ CONTRAPISO
m2
14.66
18.94
277.66
2 BORDILLO HORMIGON SIMPLE 30x10 cm
ml
23.30
7.41
172.65
3 ROTULO METALICO REFORZ 1,22x2,44
u
1.00
171.87
171.87
4 ROTULO PINTADO EN PARED
u
1.00
80.05
VARIOS
SUB-TOTAL =
QUITO, 19 DE ABRIL DEL 2010
80.05 $ 12,696.42
ABICEC CONSTRUCTORA CIA. LTDA OFERENTE
10,621.92
ANEXO HOJA 1 DE 1 ANALISIS DE PRECIOS UNITARIOS CUADRO AUXILIAR: TARIFAS DE EQUIPO
DETALLE DEL EQUIPO
COMBUSTIBLE
LUBRICANTES
REPUESTOS
MANTENIMIENTO
DEPRECIACION
OTROS
TARIFA
OPERADOR/UTILIDAD
HORARIA
CONCRETERA 1 SACO
0.25
0.25
0.50
0.50
0.75
0.75
3.00
VOLQUETA
2.50
1.50
3.00
4.00
3.00
4.00
18.00
CARGADORA FRONTAL
3.50
2.50
5.00
6.00
8.00
10.00
35.00
EXCAVADORA ORUGA
7.00
6.00
8.00
6.00
6.00
12.00
45.00
COMPACTADOR MECANICO
0.15
0.10
0.10
0.10
0.50
0.55
1.50
ANEXO HOJA 1 DE 1
CRONOGRAMA DE MANO DE OBRA
MANO DE OBRA
CANTIDAD
CATEGORIA
CAT
V
1
CAT
IV
5
CAT
III
20
CAT
II
24
CAT
I
60
TOPOGRAFO 1
1
CHOFER TIPO E
4
OEP 1
1
OEP 2
1
SIN TITULO
2
QUITO, 19 DE ABRIL DEL 2010
TIEMPO EN DIAS 30
30
30
30
30
30
30
30
30
30
#VALUE! #VALUE!
ANEXO HOJA 1 DE 1
CRONOGRAMA DE EQUIPO Y MAQUINARIA EQUIPO Y MAQUINARIA
CANTIDAD 30
CONCRETERA 1 SACO
4
VIBRADOR
2
ELEVADOR DE RIEL
2
SOLDADORA ELECTRICA
1
RODILLO COMPACTADOR
1
RETROEXCAVADORA
1
VOLQUETA 9 M3
4
EXCAVADORA DE ORUGA
1
EQUIPO TOPOGRAFICO
1
30
30
30
TIEMPO DE EJECUCION 30 30
30
30
30
30
QUITO, 19 DE ABRIL DEL 2010
ABICEC CONSTRUCTORA CIA. LTDA OFERENTE